Project to Rehabilitate Emergency Unit
At Al—Kindi Hospital / Baghdad
|
|
|
Project cost: The project cost with the additional works is about 150 0000 dollars. Project description: The project includes the following :
Work:
1. To rehabilitate the old building of emergency until totally as from re-cutting as per the newly prepared designs, preceded by demolishing the internal walls section, including all the internal & external finishes, doors, windows & all mechanical, electrical & sanitary services in addition to medical gasses systems & air conditioning works.
2. To expand the old building of floor stage & to add first floor on part of old & new building to cope with the functional changes as per the new designs.
3. To establish an independent services building opposite the old building with area of 80 M2. the area of the old building with the expansion is 1250 M2. Achievement percentage :100 %
|
|
|
|
|